BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 137 Topic 14 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 137 Topic 14 Discussion

ISEB-PM1 Exam Topic 14 Question 137 Discussion:
Question #: 137
Topic #: 14

A project becomes officially authorized when which of the following occurs?


A.

Project manager is appointed


B.

Stakeholders approve the project


C.

Project charter is approved


D.

Project sponsor approves the project