BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 131 Topic 14 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 131 Topic 14 Discussion

ISEB-PM1 Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

On what is project baseline development established?


A.

Approved product requirements


B.

Estimated project cost and schedule


C.

Actual project cost and schedule


D.

Revised project cost and schedule


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.