BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 124 Topic 13 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 124 Topic 13 Discussion

ISEB-PM1 Exam Topic 13 Question 124 Discussion:
Question #: 124
Topic #: 13

Which of the following is CORRECT about quality improvements?


A.

They are a tool of Perform Quality Assurance and an output of Verify Scope.


B.

They require the preparation of change requests or the recommendation of corrective actions.


C.

They occur only through experience of the project manager, team, and sponsor.


D.

They are a product of cooperation between the customer and the project manager.