Question #: 116
Topic #: 12
A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response.
Which of the following is the BEST thing for the project manager to do?
A.
Document the new risks and continue the Plan Risk Responses process.
B.
Make sure the project work is better understood.
C.
Spend more time making sure the risk responses are clearly defined.
D.
Get more people involved in the Identify Risks process since risks have been missed.