The following reports are normally developed during the project closure phase?
None of the other alternatives apply
Communications Management Plan and Lessons Learned
Records Archive, Closure Report, & Specifications Document
Records Archive, Closure Report, lessons learned & Formal Acceptance Report
Communications Management Plan and Closure report