ISEB-PM1 Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

Which analysis helps to determine the risks that have the most potential for impacting the project?


A.

Expected monetary value analysis


B.

Sensitivity analysis


C.

Modeling and simulation


D.

Expert judgment