New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 92 Topic 10 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 92 Topic 10 Discussion

ISEB-PM1 Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

Which analysis helps to determine the risks that have the most potential for impacting the project?


A.

Expected monetary value analysis


B.

Sensitivity analysis


C.

Modeling and simulation


D.

Expert judgment


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.