ISEB-PM1 Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

Which of the following events would result in a baseline update?


A.

Your project is behind schedule and you want your baseline to reflect estimated actual completion.


B.

Your customer has approved a change request broadening the project scope and increasing the budget.


C.

One of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.


D.

One of your key project team resources has left your team and no replacement is available.