Question #: 28
Topic #: 3

Metrics can be collected during and at the end of testing activities to assess which of the following?

i. Progress against the planned schedule and budget.

II. Current quality of the test object.

Hi. Adequacy of the test approach.

iv. Effectiveness of the test activities with respect to the objectives.

v. All the above.

Select the correct answer:


A.

Only i and ii.


B.

Only i and iii.


C.

Only I, ii and iv.


D.

Only v.