John has been working on a business case for opening up the overseas market to new products He has been asked to document the risks What SHOULD he do to ensure they are appropriately recorded? Select the TWO that apply
A.
Create a RAID log
B.
Document the source of each risk
C.
Identify an owner for each risk
D.
Provide justification or each countermeasure identified
E.
Impact assessment of each countermeasure identified
A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. To ensure that risks are appropriately recorded, they should be documented in a consistent and structured way, such as using a RAID log (Risks, Assumptions, Issues and Dependencies). A RAID log should include information such as the risk description, impact, probability, source, owner, mitigation actions, status and date. Therefore, options B and C are essential for recording risks, as they help to identify where the risk originates from and who is responsible for managing it. Option A is not relevant to recording risks, as it is the name of the tool used to document them. Option D and E are not relevant to recording risks, as they relate to the countermeasures or actions taken to address them, not the risks themselves.