Which of the following statements about an Activity Business Impact Analysis (BIA) is correct?
A.
An Activity BIA ensures that all of the activities undertaken by an organization can continue as usual during a disruption and sets out a detailed plan to enable continuity
B.
An Activity BIA determines the resources required to deliver the organization's prioritized products and services
C.
An Activity BIA identifies risks to delivery activities and establishes strategies to either prevent risks arising or to mitigate their effects should they arise
D.
An Activity BIA identifies and prioritizes the activities that deliver the most urgent products and services and determines the resources and dependencies required to enable continuity
An Activity Business Impact Analysis (BIA) is a crucial component of the Business Continuity Management System (BCMS) that focuses on identifying and prioritizing the activities within the organization that contribute to delivering critical products and services. According to the CBCI 7.0 course, the Activity BIA maps out which activities are most urgent and vital, and it determines the necessary resources and interdependencies required to maintain or restore these activities following a disruption. This detailed understanding enables the organization to allocate resources effectively and design recovery strategies tailored to priority activities. Unlike a broad process or product BIA, the Activity BIA provides granular insights into operational components, ensuring continuity plans address practical recovery needs and dependencies.
[Reference:CBCI 7.0 Study Guide, Module 3: Business Impact Analysis, pages 42-44., ]