Question #: 1
Topic #: 1

Which of the following actions will lead to the protection of priority activities with respect to their Recovery Time Objectives (RTOs) and will limit the impacts of disruptions to prioritised activities?


A.

Conducting a risk assessment


B.

Conducting an Activity Business Impact Analysis (BIA)


C.

Creating a set of approved strategies and solutions to mitigate unacceptable risks and single points of failure


D.

Grouping unacceptable risks and single points of failure by owner and having discussions with each activity and resource owner