CTS-I Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

There is a conflict between the wall plate height specified in AV documents and the height the electrical contractor is saying must be used on site. Which of the following forms would be used by the integrator to seek clarification of the correct mounting height of wall plates?


A.

Construction Change Directive (CCD)


B.

Request for Information (RFI)


C.

Request for Change (RFC)


D.

Change Order (CO)