How would a commissioning technician establish substantial completion/practical completion?
Complete all preliminary tests, confirm systems installation and readiness for final test
Generate a punch or defects list, getting architects to sign off on repairs
Generate a list of all damaged equipment, setting up the DSP
Complete a request for changes form, filing an RFQ