Which risk would pose the greatest threat to a learning project?


A.

Teamwork is faltering and the team's tolerance for change is diminished


B.

The project plan milestones are not met


C.

Actual costs are exceeding budgeted costs


D.

The key business sponsor leaves and there is no backup sponsor