CQE Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

During the causes of a problem have been verified in the analysis phase of a six sigma project, they will form the basis of the solution in Much of the following phases?


A.

Control


B.

Define


C.

Improve


D.

Measure