Question #: 89
Topic #: 9

A cross-functional team has been working t>n a process improvement project that affects departments A. B. C. and D. Once the project is completed, which of the following people associated with the team is responsible for ensuring that the changes are integrated into the processes of the affected departments?


A.

Facilitator


B.

Sponsor


C.

Member


D.

Coach