When a project team is monitoring the schedule variance of a project, which of the following is the most important question to ask first?


A.

"How much variation in the schedule did we expect initially?"


B.

Does the variance have any impact on the end date of the project?''


C.

"Do we need to reduce the scope of the project to counteract the variance?"


D.

"Will the customer allow reasonable delays in the project?”