AgilePM-Foundation Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

Identify the missing word in the following sentence.

The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.


A.

Governor


B.

Champion


C.

Visionary


D.

director