AgilePM-Foundation Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

Which purpose relates to the instrumental Success Factors?


A.

Underpins the prioritization of requirements


B.

Informs the development of the Business Case


C.

Positions DSDM projects for a successful outcome


D.

Inform the development of the Terms of Reference