Solution increments are created during the Evolutionary Development phase. This phase is where the solution is developed iteratively, building on the firm foundations laid out in the previous phases1. It involves creating increments of the product through time-boxed iterations, ensuring that the solution evolves in line with the project’s objectives and business needs.