APM Project Management Qualification (PMQ) Exam APM-PMQ Question # 12 Topic 2 Discussion

APM Project Management Qualification (PMQ) Exam APM-PMQ Question # 12 Topic 2 Discussion

APM-PMQ Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

You are the project manager for a large-scale rebranding project. During a critical phase, it becomes evident that additional funding is necessary to address unforeseen challenges.

Which role within the project would you approach to authorise the updated business case and secure the necessary funds to ensure the project's continuation?


A.

Project steering board.


B.

Product owner.


C.

Quality manager.


D.

Project sponsor.