New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 73 Topic 7 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 73 Topic 7 Discussion

APM-PFQ Exam Topic 7 Question 73 Discussion:
Question #: 73
Topic #: 7

Portfolio management includes prioritising:


A.

projects and/or programmes that contribute directly to the organisation's strategic objectives.


B.

projects with exceptionally high returns on investment.


C.

projects and programmes over business as usual.


D.

projects which maximise change over those which maximise investment


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.