Question #: 73
Topic #: 7

Portfolio management includes prioritising:


A.

projects and/or programmes that contribute directly to the organisation's strategic objectives.


B.

projects with exceptionally high returns on investment.


C.

projects and programmes over business as usual.


D.

projects which maximise change over those which maximise investment