Question #: 72
Topic #: 7

Which of the following aspects would best describe part of the project environment?


A.

The influence and interests of the key stakeholders of the project.


B.

The technical difficulties that are anticipated when undertaking the project.


C.

The circumstances within which the project is being undertaken.

D The relationship between the project manager and the project team.