New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 72 Topic 7 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 72 Topic 7 Discussion

APM-PFQ Exam Topic 7 Question 72 Discussion:
Question #: 72
Topic #: 7

Which of the following aspects would best describe part of the project environment?


A.

The influence and interests of the key stakeholders of the project.


B.

The technical difficulties that are anticipated when undertaking the project.


C.

The circumstances within which the project is being undertaken.

D The relationship between the project manager and the project team.


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.