APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 52 Topic 5 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 52 Topic 5 Discussion

APM-PFQ Exam Topic 5 Question 52 Discussion:
Question #: 52
Topic #: 5

During the consideration of when and how the development of the project management plan should take place, the objectives of carrying out such an exercise can often appear to be uncertain. As a recommendation, the project management plan should be:


A.

assembled when all information is available.


B.

developed iteratively throughout the early stages of the project.


C.

completed in detail before the project is authorised.


D.

free from detailed schedule information.


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.