If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as 'must have'?
They need to be given a special priority to ensure that they are definitely delivered.
They should have best resort to ensure they efficiently delivered.
The project could be If the delivery of these requirements were proving more difficult than expected
They would sacrificed if at any time Was to go over budget or be late