Question #: 129
Topic #: 12

A Responsibility Assignment Matrix (RAM) can be used to:


A.

define the terms of reference of the project manager.


B.

define the limits of the project sponsor's responsibilities.


C.

allocate risk management response activities to project personnel.


D.

allocate work packages to those responsible for project work.