APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 128 Topic 12 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 128 Topic 12 Discussion

APM-PFQ Exam Topic 12 Question 128 Discussion:
Question #: 128
Topic #: 12

Which one of the following statements is true?


A.

Business-as-usual activities cannot be improved.


B.

Business-as-usual activities are more difficult to manage than projects.


C.

Projects are transient endeavours that bring about change to business-as-usual.


D.

A. project is always the starting point for operational refinement.


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.