A technique to manage load variability would be to:


A.

apply capacity planning using overall factors (CPOF) to identify priority items at the work center.


B.

plan additional safety capacity as a part of total available capacity to meet unplanned demand.


C.

design the shop floor with machines that sit idle until additional demand requires their use.


D.

use capacity bills to provide a rough-cut method of planning total-time-per-unit value.