A part is sold as a service part, and it is also used as a component in another part. Which ofthe following statements aboutthe planning for this part is true?


A.

Its low-level code is zero.


B.

The material requirements for the part will be understated.


C.

The service part demand can be included in the gross requirements.


D.

It shouldn't have any safety stock.