CPIM-Part-2 Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

Marketing has requested a significant change in the mix for a product family. The requested change falls between thedemand and the planning time fences. The most appropriate action by the master scheduler is to:


A.

reject the request


B.

accept the request.


C.

forward the request to senior management.


D.

check the availability of required material.