The primary reason for tracing a component with scheduling problems to Its master production schedule (MPS) item is to:


A.

revise the rough-cut capacity plan.


B.

reschedule a related component on the shop floor.


C.

check the accuracy of the bills for the MPS items.


D.

determine if a customer order will be impacted.