According to API 936, thecontractoris responsible for submitting adetailed dryout procedure. This procedure must be reviewed and approved by the owner or the owner’s representative. While manufacturers may provide guidance, the contractor is accountable for ensuring the procedure aligns with project specifications, material requirements, and environmental conditions.
[Reference:, API Std 936, Section 6.5.1 – “The contractor shall submit a proposed dryout procedure... for review and approval.”, ]