Questions # 1:

All newly installed air-setting, hydraulic, and chemically bonded linings should be allowed to cure at the proper temperature before initial heating for a minimum of:

Options:

A.

12 hours


B.

18 hours


C.

24 hours


D.

48 hours


Expert Solution
Questions # 2:

Selection, installation, inspection, and testing of anchors shall be in accordance with:

Options:

A.

contractor's QA/QC department


B.

API RP 577


C.

welding code


D.

drawing and specifications


Expert Solution
Questions # 3:

For the qualification of the applicator/installer, they shall demonstrate their ability to install the refractory:

Options:

A.

to meet the specified quality standards utilized for the installation of work.


B.

by using the technique prescribed by the manufacturer no matter which material is used.


C.

free of visible voids, laminations on the hot face or working surface only for gunned lining.


D.

free of visible voids, laminations on the hot face or working surface only of the refractory lining.


Expert Solution
Questions # 4:

Which of the following is a valid acceptance criterion for cold crushing strength of castable used in erosive service?

Options:

A.

CCS must be no less than 80% of the manufacturer’s advertised maximum.


B.

CCS test values must average within ±10% of the manufacturer’s mean value.


C.

All individual values must exceed 75% of the manufacturer’s minimum published CCS.


D.

The lowest result must exceed 90% of ASTM C401 average for gunned materials.


Expert Solution
Questions # 5:

Who is responsible to provide details of metal fiber reinforcement including dimensions, concentration, type and metallurgy?

Options:

A.

Owner


B.

Manufacturer


C.

Contractor


D.

Inspector


Expert Solution
Questions # 6:

A layer coat of refractory lining that is applied to an existing lining in an attempt to extend the lining's life is known as:

Options:

A.

buttercoat


B.

overlay


C.

paint


D.

overspray


Expert Solution
Questions # 7:

Refractory samples cast during the mock-up are cured for a minimum of:

Options:

A.

8 hours.


B.

12 hours.


C.

18 hours.


D.

24 hours.


Expert Solution
Questions # 8:

When installing refractory castables in hot weather conditions, which of the following is acceptable? (This may have more than one correct answer; please select all that apply.)

Options:

A.

Air conditioning of ambient air


B.

Decreasing mixing time


C.

Shading of equipment and mix area


D.

Spraying water on equipment


Expert Solution
Questions # 9:

When performing the ASTM C704 and ASTM C133 refractory tests, the specimen should be fired to what temperature?

Options:

A.

815°F (435°C)


B.

1000°F (540°C)


C.

1500°F (815°C)


D.

2730°F (1500°C)


Expert Solution
Questions # 10:

Each sample tested in accordance with ASTM C181 for workability index shall consist of how many specimens?

Options:

A.

1


B.

2


C.

3


D.

5


Expert Solution