DU0-001 Exam Topic 10 Question 97 Discussion:
Question #: 97
Topic #: 10

Which risk is minimized when data center managers deploy network-critical physical infrastructure (NCPI) solutions?


A.

Downtime caused by power interruptions.


B.

Downtime caused by high speed storage.


C.

Downtime caused by poorly trained computer operators.


D.

Downtime caused by improper operational process documentation.


Get Premium DU0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.