A facility manager has to prepare a labor budget for an upcoming addition of a new patient wing. Budgetary needs will include:
— Two carpenters at $40 per hour for 20 hours a week for project work for 78 weeks
— Two carpenters at $40 per hour for 20 hours a week for maintenance work for 78 weeks
— One laborer at $20 per hour for 40 hours a week for project work for 78 weeks
— One supervisor at $45 per hour for 10 hours a week for project work for 104 weeks
— One supervisor at $45 per hour for 10 hours a week for maintenance work for 104 weeks
What is the correct budget assignment, without any benefits?