According to the AIA standard contract, final approval of shop drawings submitted by suppliers of construction materials is typically the responsibility of the
Per the AIA General Conditions of the Contract for Construction (AIA Document A201), the architect reviews and approves shop drawings, product data, and samples for compliance with design intent and contract documents. The contractor ensures submission and coordination, but final approval authority rests with the architect.
[References: AIA A201 – General Conditions of the Contract for Construction; CHFM Candidate Handbook, Planning/Design/Construction domain., , ===========, ]