AEE Certified Energy Manager (CEM) CEM Question # 23 Topic 3 Discussion
CEM Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3
Using an interest rate of 15%, an energy project has a net-present value (NPV) of $3,500. Which statement is true about the project's internal rate of return (IRR)?