Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?


A.

The primary task owner has time off logged in Workfront.


B.

The team needs to review the task before confirming the start date.


C.

The task duration and planned hours are set to begin on Friday.