Thechange management plandetails the scope of people-related activities, controls for governance, and monitoring methods for adoption and benefits realization. ACMP differentiates between the strategy (D), which defines the overarching approach, and the plan (C), which provides actionable detail. Project management plans (A) cover deliverables, not adoption. Business models (B) address strategic design, not execution controls. Thus, option C is correct.
(Reference: ACMP Standard, Process Group 3 – Develop Plan; Outputs: Scope, monitoring, and controls for change activities.)