AACE International Certified Cost Professional (CCP) Exam CCP Question # 51 Topic 6 Discussion

AACE International Certified Cost Professional (CCP) Exam CCP Question # 51 Topic 6 Discussion

CCP Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

CCP Question 51

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?


A.

10,586


B.

9,280


C.

9,559


D.

10,278