CCP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

CCP Question 16

What is the median unit cost?


A.

$48.22


B.

$48.35


C.

$40.00


D.

$46.59


Get Premium CCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.