Questions # 11:

During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.

Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)

Options:

A.

Email PDFs to the contractor every week.


B.

Update Publish Settings to include sheets.


C.

Create blank sheets for all disciplines.


D.

Enable Model Coordination.


E.

Schedule Publishes in Design Collaboration.


Expert Solution
Questions # 12:

The BIM Execution Plan (BEP) has just been completed for a new project. To ensure all multidisciplinary team members review and understand their roles and responsibilities, what is the most effective way to distribute the BEP before the project starts and ensure it remains accessible to everyone throughout the project?

Options:

A.

Include the BEP as part of the project contract and distribute it at project kickoff.


B.

Conduct a mandatory training session to review the BEP and archive it as official once approved by all disciplines.


C.

Upload the BEP to Autodesk Forma in a shared folder location to serve as a live copy.


D.

Email the BEP to all team members and request that they sign and return it as confirmation of review and agreement.


Expert Solution
Questions # 13:

The BIM manager is conducting a health check of a design model submitted by a consultant to assess its readiness for coordination. Several model performance concerns have been raised, including long open times, sluggish navigation, and excessive file size.

Which of the following actions would best help to evaluate the model’s health and identify areas of improvement?

Options:

A.

Run a performance audit using review tools and evaluate the number of warnings, file size, and modeling practices such as in-place families.


B.

Notify the consultant to reduce the model file size by deleting sheets and exporting only 3D views.


C.

Review the consultant’s coordination clash reports to determine if unresolved issues are impacting performance.


D.

Disable all linked files and re-enable them one at a time to identify which one is causing performance issues.


Expert Solution
Questions # 14:

A BIM manager is preparing to share a federated model package with an external cost estimator. The estimator only needs access to quantities and location-based metadata, but not design intent or proprietary elements from other teams.

What is the first step the BIM manager should take to ensure appropriate use and minimize data-related risk?

Options:

A.

Export the models as PDFs to prevent the third party from modifying geometry.


B.

Confirm that the model content, format, and permissions match the recipient’s defined scope of use.


C.

Verify that the file sizes are small enough for email transmission.


D.

Convert the models into 2D views to avoid exposing embedded metadata.


Expert Solution
Questions # 15:

A BIM manager is running clash detection for the first time on a large retail project during the Design Development phase. After copying all the models to the coordination space on Autodesk Forma, the matrix shows no clashes among any of the models.

How should the BIM manager proceed?

Options:

A.

Add sheets to the publish settings and rerun the clash.


B.

Verify the shared coordinates for each model and republish.


C.

Continue forward on the project because there are no coordination issues.


D.

Use the project as a case study for a firm-wide presentation.


Expert Solution
Questions # 16:

The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.

What fix needs to happen to resolve this misalignment?

Options:

A.

The BIM manager needs to go to a 3D view and move the model to align with the architectural geometry.


B.

The Lighting team needs to fix its shared coordinates to match those of the Architectural model and reissue the file.


C.

The BIM manager needs to acquire the shared coordinates of the CAD file.


D.

The Lighting team needs to add gridlines so the BIM manager can align its CAD file to the architectural gridlines.


Expert Solution
Questions # 17:

The BIM manager has finalized the BIM Execution Plan (BEP) for a multi-discipline educational facility project. Some consultants have already begun modelling, while others are onboarding late. A few external stakeholders are not listed in the original BEP distribution but will need access to coordinated models during design and preconstruction.

What two actions could be taken in order to manage distribution of updates? (Select two.)

Options:

A.

Update and reissue the BEP only to the consultants who have not yet started modelling to ensure they catch up to project standards.


B.

Formally distribute the BEP to all relevant parties as an addendum to the contract.


C.

Formally distribute the BEP to all relevant parties and confirm receipt to ensure alignment on roles, responsibilities, and agreed BIM processes.


D.

Upload the BEP in a shared Autodesk Forma Data Management folder to ensure version tracking and verify access to stakeholders.


E.

Wait until construction coordination begins before sharing the BEP with external stakeholders.


Expert Solution