Questions # 11:

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Options:

A.

Change the Task Duration Type to Effort Driven


B.

Change the Task Duration Type to Calculated Work


C.

Change the Task Constraint to Fixed Dates


D.

Change the Task Constraint to As Soon As Possible


Expert Solution
Questions # 12:

What is unique to a Scrum iteration?

Options:

A.

Backlog of stories and issues


B.

Workload Balancer for assigning users to tasks


C.

Burndown Chart


Expert Solution
Questions # 13:

A creative team accesses their assigned work in a My Tasks list report. The team would like to easily see any New tasks highlighted for visibility. How can the project manager accommodate the team’s request?

Options:

A.

Schedule a daily automatic report delivery of the New tasks in the report to the team.


B.

Create a grouping for task Progress Status and use a custom color pie chart for visibility.


C.

Create a Filter that uses conditional formatting to display New tasks only.


D.

Create a View that uses Column Rules to format the New tasks for visibility.


Expert Solution
Questions # 14:

A team lead wants to see all hours that have been logged this month by members of the team lead’s home team, organized by project. How should the team lead create this view?

Options:

A.

Navigate to a specific project and open the Hours tab. Filter the view by Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Repeat on all projects in which team members are assigned.


B.

Visit the Reports area and create a new Hour report. Add the filters for Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Group the results by Project > Name.


C.

Visit the Reports area and create a new Hour report. Add the filters for Hour > Entry Date > This Month and Project Status > Equal > Complete. Group the results by Project > Name.


D.

Visit the Teams landing page and on the Workload Balancer select the users' home team. Add the user filters for Task > Actual Start Date > This Month, click Apply. Update view settings and toggle on the Show remaining time setting.


Expert Solution
Questions # 15:

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

Options:

A.

Visit the Project page and create a new filter. Update the "Pending Approval" filter to "true" and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.


B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the "Pending Approval" filter to "true," and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.


C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to "tasks" and "issues." In the grouping tab, add a grouping for project name.


Expert Solution
Questions # 16:

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

Options:

A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.


B.

Add a new billing rate to all tasks that involve video editing.


C.

Add a new billing rate within the project.


Expert Solution
Questions # 17:

Which group of project elements can be used to monitor an active project’s progress?

Options:

A.

Gantt chart, project Condition, and Metrics


B.

Risks, planned hours, and resource utilization


C.

Project status, Updates, and Sharing


Expert Solution
Questions # 18:

Which project elements can be used to measure a project’s adherence to its original schedule?

Options:

A.

Number of tasks, actual completion dates, and project status


B.

Project baselines, planned completion dates, and actual completion dates


C.

Workload balancer data, planned completion dates, and expenses


Expert Solution
Questions # 19:

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Options:

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.


B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.


C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.


Expert Solution
Questions # 20:

What are two characteristics of a Group in Workfront? (Choose two.)

Options:

A.

A Group can be tagged in an Update thread communication.


B.

A Group assignment is not required for a user.


C.

A Group can be associated with a Company or a Project.


D.

A user can be assigned as Group Administrator of a Group.