Questions # 21:

You are serving as an Enterprise Architect at a large aerospace company. It designs, manufactures and sells civil and military aviation products worldwide and manufactures in multiple countries both inside and outside of the European Union. The company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems.

Recently, several procurement processes, within the civil aviation business, have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in change of Supply Chain Management has made the decision to consolidate and reduce redundant procurement processes and systems. He has committed to the CEO that the business will move to a "Just-in-time" procurement system so as to keep inventory costs low.

The TOGAF standard is used for internal Enterprise Architecture activities. At presents, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing procurement processes or systems.

This project is using an iterative approach for executing the Architecture Development Method (ADM). The architecture development project has completed the

Architecure Vision Phase and has started a number of iteration cycles to develop the Architecture. As a packeged application is being considered, the next iteration will include both the Business and Application Architectures.

Stakeholder concerns that should be addressed by these architectures include:

1. What groups of people should be involved in procurement-related business processes?

2. What applications will these groups use once the architecture development is complete?

3. What non-procurement applications will need to be integrated with the new procurement applications?

4. What are the dependencies between the non-procurement and the new procurement applications?

[Note: You may need to refer to the Architectural Artifacts chapter, section 31.6 (located in Part IV) within the reference text in order to answer this question.]

You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the next iteration of Architecture development.

Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?

Options:

A.

You would describe the Baseline Business Architecture with an Organization/Actor catalog, a Business Service/Function catalog, and a Data Entity/Business Function matrix. You would describe the Baseline Application Architecture with an Application Portfolio catalog and an Application/Function matrix.


B.

You would describe the Target Business Architecture with a Business Service/Function catalog, an Organization/Actor catalog, and Data Lifecycle diagrams. You would describe the Target Application Architecture with Application Communication diagrams, an Application Interaction matrix, and an Application Portfolio catalog.


C.

You would describe the Target Business Architecture with a Business Interaction matrix, and a Business Service/Function catalog. You would describe the Target Application Architecture with an Application Communication diagram, an Application/Organization matrix, an Application Interaction matrix and an Interface catalog.


D.

You would describe the Baseline Business Architecture with a Baseline Business Process catalog, and an Object lifecycle catalog. You would describe the Baseline Application Architecture with an Interface catalog and a Technology Portfolio catalog.


Expert Solution
Questions # 22:

Your role is that of the Lead Enterprise Architect at a multinational automotive corporation. The company is headquartered in Germany, and manufactures cars, trucks and buses. It has manufacturing plants across North America, South America, Europe and Asia. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.

The company has an ongoing initiative to improve the efficiency of all of its production operations, and in particular to reduce its carbon footprint. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in energy usage could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in one central data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities.

The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are based on the TOGAF standard. At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the global

CIO. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.

You have been asked to select the most appropriate recommendation to ensure that the team evaluated different approaches to the problem and clarifies the requirements for the architecture.

Based on the TOGAF standard, which of the following is the best answer?

Options:

A.

The team should identify the individuals and groups within the organization who will contribute to the project, in order to understand who has concerns about the initiative. The team should then hold a series of interviews at each of the manufacturing plants using the business scenario technique. This will then enable them to identify and document the key high-level stakeholder requirements for the architecture.


B.

The team should exercise due diligence and carefully research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier list. Based on the findings from the research, the team should define a preliminary Architecture Vison. The team should then use that model to build concerns among the key stakeholders.


C.

The team should perform a shallow architecture development iteration, developing Baseline and Target Architectures for each of the manufacturing plants. This should include development of a set of views corresponding to selected viewpoints that address key concerns of the stakeholders. A consolidated gap analysis between the architectures will then be used to validate the approach, and determine the capability increments needed to achieve t


D.

The team should utilize its approved supplier list, and conduct a pilot project that will enable those suppliers to demonstrate potential solutions that will address the concerns of the stakeholders. Based on the findings of that pilot project, a complete set or requirements will be developed that will drive the evolution of the architecture.