Questions # 1:

Scenario:

Please read this scenario prior to answering the Question

You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.

The firm has traditionally allowed each manufacturing plant to drive its own production planning systems. Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.

"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.

As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.

The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.

Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.

Refer to the Scenario

You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored Content Metamodel. As the environment is process-centric this will enable them to model the manufacturing processes and store information to support regulatory compliance. It also includes views useful for managing the consolidation of applications into a single data center.


B.

You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change that will impact its operational models. This will ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.


C.

You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamodel. This would allow modeling of the target milestones they want to achieve with this consolidation of application to a single data center. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.


D.

You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamodel. This would allow modeling of the location of IT assets and ensure regulatory compliance for the manufacturing process. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.


Expert Solution
Questions # 2:

Scenario

Please read this scenario prior to answering the question

You are serving as the Lead Architect for the enterprise architecture team at a large multinational aerospace and defense company. The company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Several procurement processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant procurement processes and systems. The company will move to a "Just-in-time" procurement system so as to keep inventory costs low.

TOGAF 9 is used for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).

At present, there are no particularly useful architectural assets in the Architecture Repository that are related to this initiative. All assets will need to be acquired, customized, or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing procurement processes or systems.

The architecture development project has completed the Preliminary Phase and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:

1. What groups of people should be involved in procurement-related business processes?

2. What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?

3. What non-procurement applications will need to be integrated with any new procurement applications?

Refer to the Scenario

[Note: You may need to refer to Chapter 35 of the reference text in order to answer this question.]

You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the next iteration of Architecture development.

Based on TOGAF, which of the following is the best answer?

Options:

A.

In the next iteration of Architecture development, you would describe the Baseline Business Architecture with a Business Service/Function catalog, an Organization/Actor catalog, and a Data Entity/Business Function matrix. You would describe the Baseline Application Architecture with an Application/Function matrix.


B.

In the next iteration of Architecture development, you would describe the Target Business Architecture with a Business ServiceFunction catalog, an Organization/Actor catalog, and Data Lifecycle diagrams. You would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix.


C.

In the next iteration of Architecture development, you would describe the Target Business Architecture with a Business ServiceFunction catalog, a Business Interaction matrix, and Product Lifecycle diagrams. You would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix.


D.

In the next iteration of Architecture development, you would describe the Baseline Business Architecture with a Baseline Business Process catalog, and an Object lifecycle catalog. You would describe the Baseline Application Architecture with a Technology Portfolio catalog.


Expert Solution
Questions # 3:

Patterns & Co. is introducing a Commercial Off-the-Shelf (COTS) Market Analytics solution in order to improve its new delivery service.

Patterns & Co. has a mature enterprise architecture capability and the CIO is the sponsor of the enterprise architecture team. The business vision and requirements for the new system are defined. It includes a detailed business process analysis. The supplier has proposed a solution but the Architecture Board identified some of the project requirements not consistent with the adopted infrastructure standards. The CIO considered the risks and approved the implementation.

The CIO has asked the EA team to execute the Phase G ensuring that the system performance KPIs are respected, the project remains within budget and security guidelines are met.

Refer to the scenario above

As Lead Enterprise Architect you have to recommend a plan to implement the CIO decision. Choose the best answer according to TOGAF 9.

Choose one of the following answers

Options:

A.

You ask the supplier to modify the web server hardware and software components so they can meet the current infrastructure standards. You advise to execute a proof of concept to anticipate any coding issue. Then, after the agreement with the development leads for supporting the development, you will provide the project plan to the project manager and develop an Architecture Contract. A set of frequent operational reviews to monitor the solu


B.

You recommend the co-existence of a second web server standard and modify the company Standards Information Base adding this new technology.You ask the project architects to create an Architecture Contract with the development teams. You identify the need of a performance testing and a compliance review You agree with the business on SLA and delivery dates. You identify re-usable procedures and objects.


C.

You eliminate the non-standard web server from the solution as recommended by the Architecture Board. You create a revised plan and Architecture Contract for the development stressing the re-use of standard technologies. You share the budget implication of this solution with a finance committee and inform the CIO of the long term cost benefits of this choice. You define periodical project management meetings to monitor compliance.


D.

You execute a risk analysis and set deliverables and timing requirements with the development team. You implement a detailed impact analysis of the chosen solution. You create an Architecture Contract and ask for the CIO's approval before implementing it. You test the solution just prior to implementation and deliver the project artifacts and store after the completion of the implementation.


Expert Solution
Questions # 4:

Scenario: Marona Inc.

Marona Inc is a Fortune 500 Enterprise in the retail industry with retail store components manufacturing units and marketing outlets spanning the globe and having an annual turnover of 20 billion$ with more than 100, 000 employees world wide.

The CEO, CIO and the stakeholders of the ongoing EA projects are concerned about rising costs and as one measure want to do an investigation into the operational aspects of the realized Enterprise Architecture using TOGAF9.

The CIO approaches you as the Lead Enterprise Architect to carry out this exercise the stakeholder had voiced to him the following concerns:

They want to analyze the roles of the top management for each revenue earning service. Moreover, many of the HR related critical Search application component have become extremely slow. This needs to be diagnosed and rectified. Moreover there is no proper tracking of revenue from retail store component products over time. There has also been a lot of unauthorized or unwanted access to many of the critical information.

Hence the mode of access needs to be strengthened and made much more secure. Another additional concern is the new launches and the progress of each of the launches over time.

Determine which of the following set of viewpoints are most appropriate to analyze and view in order to address this concern of the stakeholders.

Options:

A.

(i) System/Functions Matrix(ii) Actor/Role Matrix(iii) Data Entity/Business Function Matrix(iv) Technology Portfolio Catalog(v) Data Security Diagram


B.

(i) Goal/Objective/Service Diagram(ii) Contract Measure Catalog(iii) Data Dissemination Diagram(iv) Application Communication Diagram(v) Data Life Cycle Diagram


C.

(i) Location Catalog(ii) Service/Function Catalog(iii) Data Entity/Business Function Matrix(iv) Application Communication Diagram


D.

(i) System/Functions Catalog(ii) System/Technology Matrix(iii) Goal/Objective/Service Diagram(iv) Product Life Cycle Diagram(v) Data Security Diagram


Expert Solution
Questions # 5:

FreshFruit Int. is an online American grocer. The Executive Board decided to implement a new strategy to expand the business to other markets.

The CIO is sponsoring an enterprise activity to support the expanded operations.

A new solution is rolled-out to replace the legacy online sales platform. A compliance review was performed to assess the solution implementation.

The result of the review highlighted a complaint from the development team stating that the new system is difficult to integrate with the existing warehouse automation systems. The Chief Architect is concerned that the complaint is not related to a real problem of the solution but is based on personal preferences of the development teams. Another interview with the project team is scheduled.

Refer to the scenario above

You are the Lead Architect and an architect from your team leads the review team. You have to answer how, based on TOGAF 9, you should enable the review team to conduct the reviews successfully.

Choose one of the following answers

Options:

A.

Meeting with the project architect you clarify the purpose of the review. You ask to perform an objective and fair review using the checklists to frame the review and clarify that you want them to identify the issues behind the implementation team complaints.


B.

You organize a meeting with the review team and state the importance to identify any non-compliancy that may have come from the implemented solution.


C.

You organize a meeting with the review team and stress the importance of a high degree of compliance without any exception. The review should cover every aspect of the implementation and should criticize the implementation techniques.


D.

You verify that criteria for the program and the business objectives are mapped in the checklists that the project team prepared for the interviews. You confirm the checklist content to the project architect and stress the need to be objective and fair during the review process.


Expert Solution
Questions # 6:

Scenario: Vittronics Ltd.

Please read this scenario prior to answering the question

Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.

This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.

The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.

The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.

The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.

The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.

Refer to the Vittronics Ltd Scenario

You are serving as the Lead Architect for the SPICE project team.

You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).

Based en TOGAF 9, which of the following is the best answer?

Options:

A.

Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability


B.

Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRLO matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule


C.

Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.


D.

Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. Document the progression of the enterprise architecture using an Enterprise Architec


Expert Solution
Questions # 7:

Scenario:

Please read this scenario prior to answering the Question

You have been assigned the role of Chief Enterprise Architect within a leading North American information technology services company. The company has a number of service portfolios including infrastructure, applications, business process outsourcing, accounting, and financial services.

With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management within the company has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings.

The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of an Enterprise Architecture prog-am based on TOGAF 9. An Architecture Board has been formed comprised of IT staff executives and executives from the major practice areas.

The Enterprise Architecture team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.

The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the senior partners that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.

Refer to the Scenario

You have been asked to recommend an approach to satisfy these concerns.

Based on TOGAF 9, which of the following is the best answer?

Options:

A.

You recommend that before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required to achieve the proposed Target Architecture. The EA team should assess the readiness of the organization to undergo change. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution t


B.

You recommend that the EA team apply an interoperability analysis to evaluate any potential issues across the Solution Architecture. This should include the development of a matrix showing the interoperability retirements. Once all of the concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.


C.

You recommend that the EA team apply the Business Transformation Readiness Assessment technique which will allow the risks associated with the transformations to be identified and mitigated for, it will also identify improvement actions to be worked into the Implementation and Migration Plan. A Business Value Assessment should be used to determine the business value and associated risks for the transformation.


D.

You recommend that the EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.


Expert Solution
Questions # 8:

You are working as a consultant to the Chief Architect at an intelligent and security organization responsible for securing government communications and information systems. These provide real-time, highly secure communication of voice, video, and message data to remove locations around the world. The agency has recently received information from intelligence sources that the current encryption protocols may no longer be secure. In response, a program is underway to upgrade the systems.

The agency has an established Enterprise Architecture (EA) capability based on the TOGAF standard. The Executive Director of the agency is the sponsor of the

EA capability.

Since reliable, high-preformcane, and secure communications are essential to be preserving national security, the Executive Director has placed stringent requirements for the architecture of the upgraded systems. It must be able to provide assurance of the upgraded systems. It must be able to provide assurance and verification of specific performance measures on the key services that are most crucial for system operation. Focusing on these service-level details and specific measurements will allow stricter requirements to be enforced in service contracts. It will also provide a high degree of assurance that necessary performance is being delivered and that notifications will occur if any critical service fails to perform as required.

A portion of the program budget has been allocated to conduct a review of the EA. The scope of the review is to evaluate the processes, content, and governance of the EA capability to ensure that the higher target performance and service levels required by the upgraded system can be achieved.

The Chief Architect has noted that the core EA artifacts that have been in use are not able to describe these new capabilities. The artifacts do not have explicit provisions for defining the in-depth measurement requirements regarding specific services required for the system. She has learned that certain services within the current system have service measurement implemenations that match some of the new requirements, but they are only used in a few areas.

Recent EA efforts at another national agency have produced generalized high-performance communication system models to realize similar requirements in a critical defense system involving secure communications. It is possible that these models may be useful for the upgrade program.

[Note: You may need to refer to the Content Metamodel chapter, section 30.4 (located in Part IV) of the reference text in order to answer this question.]

You have been asked to make recommendations for tailoring the Architecture Content Metamodel to accommodate the requirements of the upgraded system.

Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?

Options:

A.

You recommend that the motivation and governance extensions are incorporated into the Architecture Content Metamodel. Using these extensions will allow modeling the goals, objectives and drivers for the architecture, linking them to servive levels and more detailed governance models. This will also enable the ability to re-use existing profiles, customizing them for the various service contracts involved.


B.

You recommend that a Communications Engineering view is created using the infrastructure consolidation extension from the Architecture Content Metamodel. This view will allow architects to align the needed performance measurement communications across the system. This will support the stringent performance measurements needed for the more detailed governance views required for the upgraded system, making the interfaces to the communication


C.

You recommend all of the extensions be incorporated into the Architecture Content Metamodel. The full Content Metamodel will enable the EA team to capture and categorize all the important additional data neded to support the performance and measurement objectives linked to these artifacts. Once the new repository content has been implemented, on-demand queries can be used to generate a customized governance stakeholder view that isolated th


D.

You recommend that the services extension be incorporated into the Architecture Content Metamodel. By using this extension, the service model is no longer constrained by what is expected in typical business service defintions, allowing more flexibility for adding customized models to support the more stringent measurement requirements. The services extension can also be used to map terminology between the business services and the applicati


Expert Solution
Questions # 9:

You are serving as the Lead Architect for an Enterprise Architecture project team within a multinational oil and gas corporation. It is organized into two major business groupings:

✑ Upstream operations which include exploration for crude oil and natural gas and operating the infrastructure necessary to deliver oil and gas to the market

✑ Downstream operations which include the manufacturing, distribution and marketing activities for oil products and chemicals. Safety is a priority for the company, with the aim to ensure it causes zero harm to people and the environment. The company has to satisfy the regulatory requirements of each of the countries it operates in.

The downstream business generates a third of the company's profits worldwide and includes more than 30,000 petrol stations and various oil refineries. In some countries it also includes oil refining, a retail petrol station network, lubricans manufacture and marketing, industrial fuel and lubricans sales. The practice for the downstream business has been to operate locally, managed by local "operating companies".

The Governing Board is concerned about the risk posed by operating in this complex global environment with a large part of the downstrean business represented by local operating companies. As a result, the Chief Executive Officer (CEO) has appoimted a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues to the corporation. The CCO reports directly to the CEO.

The CCO has approved the expenditure of resources to establish an Enterprise Architecture program, and has mandated the use of the TOGAF standard as the framework. He has requested to be

You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance

Officer, legal staff, auditors and the local operating companies.

Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?

Options:

A.

You recommend that an analysis of the stakeholders is undertaken, including development of a Stakeholder Map. This will allow the architects to define groups of stakeholders who have common concerns. The concerns and relevant viewpoints should then be defined for each group of stakeholders, and recorded in the Architecture Vision document.


B.

You recommend that the ArchiMate modeling language is used to create a set of models that can be applied uniformly across all architecture projects. Each architecture should then be defined based on this fixed set of models. All concerned parties can then examine the models to ensure that their needs have been addressed.


C.

You recommend that a set of models be created for each project architecture that can be used to ensure that the system will be compliant with the local regulations. A formal review should be held with the stakeholders to verify that their concerns have been properly addressed by the models.


D.

You recommend that a Communications Plan be created to address the powerful and influential stakeholders. This plan should include a report that summarizes the key features of the architecture with respect to each location and reflect the stakeholders' requirements. You will check with each stakeholder that their concerns are being addressed.


Expert Solution
Questions # 10:

Scenario

Please read this scenario prior to answering the question

You are working as a consultant to the Chief Architect at a government agency responsible for securing all government communications and information systems. The agency has recently received funding for a program that will upgrade the reliability and performance of its secure communication systems which provide real-time, highly secure communication of voice, video, and message data to remote locations around the world.

The agency has an established enterprise architecture (EA) capability based on TOGAF 9. The Executive Director of the agency is the sponsor of the EA capability.

Since reliable, high-performance, and secure communications are essential to preserving national security, the Executive Director has placed more stringent requirements for the architecture for the upgraded system. It must be able to provide assurance and verification of specific performance measures on the key services that are most crucial for system operation. Focusing on these service-level details and specific measurements will allow more stringent requirements to be enforced in service contracts. It will also provide a high degree of assurance that necessary performance is being delivered and that notifications will occur if any critical service fails to perform as required.

A portion of the program budget has been allocated to conduct a review of the EA. The scope of the review is to evaluate the processes, content and governance of the EA capability to ensure that the higher target performance and service levels required by the upgraded system can be achieved.

The Chief Architecture has noted that the core EA artifacts that have been used since TOGAF 9 was introduced are not adequate to describe these new capabilities. The artifacts do not have explicit provisions for defining the in-depth measurement requirements regarding specific services required for the system. She has learned that certain services within the current system have service measurement implementations that match some of the new requirements, but they are only used in a few areas.

Recent EA efforts at another national agency have produced generalized high-performance communication system models to realize similar requirements in a critical defense system involving secure communications. It is possible that these models may be useful for the upgrade program.

Refer to the Scenario

You have been asked to make recommendations for tailoring the Architecture Content Metamodel to accommodate the requirements of the upgraded system.

Based on TOGAF, which of the following is the best answer?

Options:

A.

Since some artifacts will now require specific measurements and additional data will be needed to support the performance objectives linked to these measurements, you recommend that the motivation and governance extensions of the TOGAF 9 Content Metamodel are used. Using these extensions will allow modeling the goals, objectives and drivers for the architecture, linking them to service levels and more detailed governance models. This will a


B.

You recommend all of the TOGAF 9 Content Metamodel extensions be incorporated into the Architecture Content Metamodel. The full Content Metamodel will enable the EA team to capture and categorize all the important additional data needed to support the performance and measurement objectives linked to these artifacts. Once the new repository content has been implemented, on-demand queries can be used to generate a customized governance stakeh


C.

Since this case requires extensions of the modeling and data details of the service, this is best done by using the services extension of the TOGAF 9 Content Metamodel. By using this extension, the service model is no longer constrained by what is expected in typical business service definitions, allowing more flexibility for adding customized models to support the more stringent measurement requirements. The services extension can also be


D.

To support the type of stringent performance measurements needed for the more detailed governance views required for the upgraded system, the interfaces to the communication and network layer of the architecture must be highly visible at the application level. To accommodate the proper development of this, a Communications Engineering view should be created from the infrastructure extension models of the TOGAF Content Metamodel. This view w