Questions # 11:

Which of the following are available in the initial SAP Methodologies JAM Page? There are 2 answers to this question.

Options:

A.

Accelerators


B.

Roadmaps


C.

Task description


D.

Summary


Expert Solution
Questions # 12:

What can you see in the process content viewer?

Options:

A.

Business user roles


B.

Business process models


C.

Business process value flows


D.

SAP Activate tasks


Expert Solution
Questions # 13:

What are some extension item types can be transported from the Quality system to the Production system?

Options:

A.

Custom Fields


B.

Custom Business Logic


C.

Form Templates


D.

Query Designer Report


E.

Communication Arrangements


F.

Master Data


G.

Employee Data


Expert Solution
Questions # 14:

In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the answer.

Options:

A.

Fit/Gap Workshops


B.

Custom Extension management


C.

Business Process Mapping


D.

Value Determination


Expert Solution
Questions # 15:

Which types of tests are supported by Test Management in SAP Cloud ALM? Note: There are 2 answers to this question.

Options:

A.

Acceptance testing


B.

Integration of automated testing


C.

Manual testing


D.

System testing


Expert Solution
Questions # 16:

Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.

Options:

A.

System consolidation


B.

Consolidation through online data replication


C.

Security migration


D.

Extraction of business units


E.

System upgrade


Expert Solution
Questions # 17:

Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 answers to this question.

Options:

A.

Configuration guides


B.

Building blocks


C.

Scope items


D.

Business process scenarios


Expert Solution
Questions # 18:

In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape?

There are 2 answers to this question.

Options:

A.

Starter system


B.

QAS


C.

P-system


D.

DEV


Expert Solution
Questions # 19:

What are the elements in the SAP Activate Implementation Framework?

Options:

A.

Methodology


B.

Tools


C.

Content


D.

Analytics


Expert Solution
Questions # 20:

Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.

What is the sequence of selected key deliverables across the project phases? Please choose the answer.

Options:

A.

2nd option


B.

Production Readiness Check


C.

Detailed system Assessment


D.

Code Adjustment


E.

Validation of Migration


F.

4th option


G.

Detailed system Assessment


Expert Solution