Questions # 11:

Universal Container has multiple departments who use Salesforce and request changes: Sales, Service, Back Office, Marketing, etc. Each of these departments makes independent purchase decisions for AppExchange apps, field requests, and page layouts, resulting in low adoption and under -use of standard Salesforce capabilities. What mechanism should a Technical Architect recommend to increase use of standard Salesforce functionality?

Options:

A.

Change Control Board


B.

Requirements Traceability Matrix


C.

Center of Excellence


D.

Project Management Office


Expert Solution
Questions # 12:

Universal Containers has 80% code coverage. Despite the creation of a test plan for

each sprint, the number of defects is large.

What two items should the architect recommend to reduce defects?

Choose 2 answers

Options:

A.

The test script should be used to define the test classes.


B.

The code coverage should be increased to 95%.


C.

The test analyst who creates the test plan must also create the test classes.


D.

The acceptance criteria should have more details.


Expert Solution
Questions # 13:

Universal Containers (UC) is midway through a large enterprise project. UC is working

in an agile model, and currently has four-week iterations, with a branching strategy supporting

this approach. UC operates in a strict regulatory environment, and has dedicated teams for

security, QA, and release management. The system is live with users, and a serious production

issue is identified at the start of a sprint, which is narrowed down to a bug in some Apex code.

Which three approaches should an architect recommend to address this bug?

Choose 3 answers

Options:

A.

Investigate potential data impacts.


B.

Fix the bug in a hotfix branch.


C.

Wait until the next release to deploy the fix.


D.

Attempt to fix the bug directly in production.


E.

Seek stakeholder approval for the hotfix.


Expert Solution
Questions # 14:

Universal Containers CUC) is looking for advice on how often it should refresh its sandboxes. UC currently uses a development Mfecycle that starts with developer environments and moves to integration testing, QA testing, UAT, and then production. They have many scrum teams working concurrently and the teams do not agree on when refreshes should occur.

What two recommendations should the architect suggest?

Choose 2 answers

Options:

A.

Sandboxes should be refreshed on the day when the refresh is allowed for that type of sandbox.


B.

Production is the only pristine environment.


C.

Integration sandboxes should be refreshed rarely because of the burden of maintaining the various API.


D.

Development environments should generally be refreshed after each working feature has been successfully migrated.


Expert Solution
Questions # 15:

Universal Containers has a full sandbox that will be used to analyze and fix bugs found

in production.

Which two items should the architect recommend to ensure that bugs found in production are

more easily analyzed in this full sandbox?

Choose 2 answers

Options:

A.

Refresh the full sandbox after every deployment in production.


B.

Create a daily process of copying new and changed data in production to the full sandbox.


C.

Before any deployment in production, the same process must be performed in this sandbox.


D.

Perform a Refresh Data in the full sandbox.


Expert Solution
Questions # 16:

Which statement is true for the Staging sandbox in the following diagram?

Question # 16

Options:

A.

When created or refreshed, the Staging sandbox is a full replica of Production


B.

The Staging sandbox is automatically refreshed on a schedule set by the administrator


C.

Salesforce major releases (e.g., Winter to Spring) always occur in Staging and Production at the same time


D.

The Staging environment can only be updated once every two weeks


Expert Solution
Questions # 17:

Universal Containers (UC) is developing a new Customer Community. Requirements for the Community are not fully defined. UC is planning on using an Agile methodology for this work and has promised delivery of the complete system in three months. What are two risks associated with this approach? Choose 2 answers

Options:

A.

The functionality that can be delivered in 3 months is unknown, and may not meet the needs of the business


B.

Given the lack of requirements and the three-month timeline commitment, the project may not be feasible


C.

Agile is not an appropriate development methodology for Customer Community implementations


D.

Agile does not allow for changes to requirements, so customers might not like the resulting solution


Expert Solution
Questions # 18:

What are three advantages of the package development model?

Choose 3 answers

Options:

A.

Improving team development and collaboration.


B.

Eliminating the need of using change set, which should no longer be used as it can get messy working with package development models.


C.

Facilitating automated testing and continuous integration.


D.

Significantly reducing the need for manually tracking changes.


E.

Providing its own source control, so the source can be deployed In any sandbox orgs.


Expert Solution
Questions # 19:

An architect is working on a Universal Containers (UC) project, and due to security

concerns, the UC security team cannot provide the

Architect with production access. Instead, a central release management team will be responsible

for performing production deployments for all development teams.

How should an architect leverage the Metadata API to ensure any metadata components

necessary to deploy the project’s functionality

Are properly communicated to the release management team?

Options:

A.

Provide a spreadsheet of all components and utilize the metadata API’s read Metadata()call.


B.

Communicate the unlocked package version to the release management team.


C.

Create a change set in each sandbox and download the package.xml file for the release management team.


D.

Provide the release management team a copy of the audit trail from the sandbox you wish to deploy from.


Expert Solution
Questions # 20:

Universal Containers has recently acquired another business that uses Salesforce extensively. UC wants to merge their Salesforce Orgs to effectively sell and service customer under one business. Traditionally, UC has followed an agile development methodology to deliver Salesforce functionality. With the merging businesses, UC is convinced that adopting a Waterfall development methodology is the best approach. Which are two positive aspects of using a Waterfall development methodology?

Options:

A.

Changes late in the process are expected and can be handled by integrating them into the requirements specs.


B.

Complex processes that will need to be built are thoroughly understood and documented before coding begins.


C.

Milestones, timelines and estimates tend to be more accurate and predictable due to the upfront due diligence.


D.

The costs of starting the project are low since much of the design work is pushed to later stages of the process.


Expert Solution