Questions # 11:

After OEM completes tracking a work order and the supply is available, who sends the shipping req and to whom?

Options:

A.

OEM to CM


B.

Production Supervisor to CM


C.

Production Supervisor to OEM


D.

CM to OEM


Expert Solution
Questions # 12:

Three correct statements with respect to Demand fulfillment view in supply plan are?

Options:

A.

Users need to define the criteria and layout in the view


B.

View prioritized at-risk demands based on order values weighted by the numberof associated recommendations


C.

User can take actions on the demand fulfilment recommendations by accepting recommendations


D.

The recommendation summary graph shows the cumulative at-risk demand value and the related number of recommendations associated with that value


Expert Solution
Questions # 13:

Which three pieces of demand information can be included as demand in an Oracle supply plan?

Options:

A.

Production Plan


B.

Build Plan


C.

Manual Forecast


D.

Demand Forecast


Expert Solution
Questions # 14:

What represents a Physical, Geographical, or Logical Cluster of Work Centers?

Options:

A.

Resource Instances


B.

Resources


C.

Work Area


D.

Manufacturing Calendar


Expert Solution
Questions # 15:

What are the planning levels available for Min-Max planning?

Options:

A.

Organization and Sub inventory


B.

Organization, Sub inventory, Locator, Project, and Item


C.

Organization, Sub inventory, Locator, and Item


D.

Organization, Sub inventory, and Locator