Questions # 41:

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.

The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.

You need to resolve the issue.

What should you do?

Options:

A.

Increase positive days.


B.

Decrease positive flays.


C.

Decrease negative days to be less than the item lead time.


D.

Increase negative days to be greater than the item lead time.


Expert Solution
Questions # 42:

A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.

The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.

The organizational entities are:

• LegalEntityA: Plant 1.2, and 3

• LegalEntityB: Plant4and 5

• LegalEntityC: Plant 6. 7, and 8

The following plants must be planned together:

• Plant 1. Plant 3. and Plant 4

• Plant 2. Plant 6. and Plant 8

• Plant 5 and Plant 7

You need to configure master planning for the facilities.

Which configuration mechanism should you use?

Options:

A.

Production groups


B.

Item model groups


C.

Coverage groups


D.

Intercompany planning groups


Expert Solution
Questions # 43:

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.

The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. Ingredient A is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.

You need to ensure that the system is set up to support the manufacturing process.

Solution: Create a dimension-based product with configurations. Use a price model to calculate the different configurable option costs.

Does the solution meet the goal?

Options:

A.

Yes


B.

No


Expert Solution
Questions # 44:

A pharmaceutical company is implementing Dynamics 365 Supply Chain Management.

The formulas for medication include a single active ingredient. The active ingredient will be defined with a target level and specified deviation ranges from the target.

You need to set up the active ingredient items.

Which two actions must you perform? Each answer presents a partial solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Configure expiry dates for a batch.


B.

Configure inventory batch attributes.


C.

Enable serial tracking.


D.

Enable batch tracking.


Expert Solution
Questions # 45:

You are developing a new car audio system kit. The kit configuration has restrictions based on car model, speaker size, and other expression constraints.

You need to set up a new item for the car audio system.

How should you create the new product? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Question # 45


Expert Solution
Questions # 46:

A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You create the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.

You need to set up a new item model group for the service item.

Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question # 46


Expert Solution
Questions # 47:

A company uses Asset management in Dynamics 365 Supply Cham Management. The company also uses Dynamics 365 Guides independently of the Dynamics 365 Supply Chain Management implementation.

Maintenance workers requite a checklist template to complete work orders. A solution must help the workers through work order steps. The solution must use Dynamics 365 Guides with Dynamics 365 Supply Chain Management.

You need to integrate the solution.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question # 47


Expert Solution
Questions # 48:

A company has a Dynamics 365 Supply Chain Management implementation. The company plans a promotional sales campaign that targets top customers.

The sales campaign will guarantee that orders are delivered within a specific two-week period.

The system configuration must prioritize a group of similar production orders so they can be scheduled at the same time.

You need to configure the system.

What should you create?

Options:

A.

Production pool


B.

Production flow model


C.

Production unit


D.

Production group


Expert Solution