Questions # 136:

John and Hanna are business analysts in their organization and they are completing the verification activities to check for completeness of the requirements. When should John and Hanna perform these verification activities?

Options:

A.

At each milestone of the requirements analysis process


B.

Once all of the requirements have been gathered


C.

Iteratively throughout the requirements analysis process


D.

As often as the requirements management plan calls for


Expert Solution
Questions # 137:

Nancy has asked you to trace a particular requirement for her. What does 'to trace a requirement' mean?

Options:

A.

Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to components in the project's work breakdown structure.


B.

Tracing a requirement means to track a requirement from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement.


C.

Tracing a requirement means to look at a requirement and the others to which it is related. It links risk, cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components.


D.

Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution components.


Expert Solution
Questions # 138:

The initial high-level listing of requirements in a change-driven approach is also known as what?

Options:

A.

Requirements envisioning


B.

Requirements foundation


C.

Product scope


D.

Project scope


Expert Solution
Questions # 139:

Some of the requirements in the solution must be completed because of laws and regulations in your industry.

Management would like you, the business analyst, to rank the requirements according to the relevant laws. What type of requirements prioritization is management having you complete?

Options:

A.

Business value ranking


B.

Risk ranking


C.

Constraint ranking


D.

Regulatory ranking


Expert Solution
Questions # 140:

Which one of the following is not an event-based elicitation technique?

Options:

A.

Focus group


B.

Interface analysis


C.

Interview


D.

Workshop


Expert Solution
Questions # 141:

There are three inputs for stakeholder analysis. Which input describes the organizational units that exist and their interactions with one another?

Options:

A.

Business need


B.

Enterprise architecture


C.

Matrix structure


D.

Organizational process asset


Expert Solution
Questions # 142:

You are the business analyst for your organization and you and your staff are creating as many solutions as possible to an identified problem in the solution approach process. What is this activity element called?

Options:

A.

Alternative generation


B.

Brainstorming


C.

Prototyping


D.

Lateral thinking


Expert Solution
Questions # 143:

Beth is the business analyst for her organization and she's creating a data dictionary for her organization. All of the following information should be included in the data dictionary for an endeavor Beth is leading except for which one?

Options:

A.

Description


B.

Aliases


C.

Name


D.

Code of account identifier


Expert Solution
Questions # 144:

You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback. Which of the following statements best describes the change-driven approach?

Options:

A.

The change-driven approach favors defining requirements through experimentation.


B.

The change-driven approach favors defining requirements standardized templates.


C.

The change-driven approach favors defining requirements through team interaction.


D.

The change-driven approach does not define the requirements until after a solution for the problem has been identified.


Expert Solution
Questions # 145:

According to 'A Guide to the Business Analysis Body of Knowledge', the two most common data models are the entity-relationship diagram and what other model?

Options:

A.

Class model


B.

Project network diagram


C.

Data flow diagram


D.

WBS


Expert Solution
Questions # 146:

Which one of the following statements best describes a business analysis methodology?

Options:

A.

It is the conformance to requirements and a fitness for use.


B.

It is a formalized and repeatable business analysis approach.


C.

It specifies team roles, deliverables, analysis techniques, and the timing and frequency of stakeholder interactions.


D.

It is a complete set of action, processes, and output to collect, analyze, and prioritize the project requirements.


Expert Solution
Questions # 147:

You are the business analyst for your organization. You're creating a document that states the business need, identifies the key stakeholders, and defines the positive impact the solution will bring to the organization and stakeholders. What document are you creating?

Options:

A.

Requirements documentation


B.

Business case


C.

Project charter


D.

Vision statement


Expert Solution
Questions # 148:

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record these communication requirements based on your stakeholder analysis?

Options:

A.

Project schedule


B.

Project scope management plan


C.

Project reporting structure


D.

Project communications management plan


Expert Solution
Questions # 149:

A global organization is implementing a new Knowledge Management System, and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?

Options:

A.

Email


B.

Repository


C.

Document management


D.

Individual collaboration


Expert Solution
Questions # 150:

A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?

Options:

A.

Backlog management


B.

Balanced scorecard


C.

Concept modeling


D.

Requirements architecture


Expert Solution