John and Hanna are business analysts in their organization and they are completing the verification activities to check for completeness of the requirements. When should John and Hanna perform these verification activities?
Nancy has asked you to trace a particular requirement for her. What does 'to trace a requirement' mean?
The initial high-level listing of requirements in a change-driven approach is also known as what?
Some of the requirements in the solution must be completed because of laws and regulations in your industry.
Management would like you, the business analyst, to rank the requirements according to the relevant laws. What type of requirements prioritization is management having you complete?
Which one of the following is not an event-based elicitation technique?
There are three inputs for stakeholder analysis. Which input describes the organizational units that exist and their interactions with one another?
You are the business analyst for your organization and you and your staff are creating as many solutions as possible to an identified problem in the solution approach process. What is this activity element called?
Beth is the business analyst for her organization and she's creating a data dictionary for her organization. All of the following information should be included in the data dictionary for an endeavor Beth is leading except for which one?
You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback. Which of the following statements best describes the change-driven approach?
According to 'A Guide to the Business Analysis Body of Knowledge', the two most common data models are the entity-relationship diagram and what other model?
Which one of the following statements best describes a business analysis methodology?
You are the business analyst for your organization. You're creating a document that states the business need, identifies the key stakeholders, and defines the positive impact the solution will bring to the organization and stakeholders. What document are you creating?
You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record these communication requirements based on your stakeholder analysis?
A global organization is implementing a new Knowledge Management System, and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?
A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?