Questions # 31:

Some new carpets can emit volatile organic compounds (VOCs) that can adversely affect occupants.

How can the facility manager avoid this problem when purchasing new carpeting?

Options:

A.

Research emissions data from carpet manufacturers.


B.

Increase the air flow in the space.


C.

Allow at least one month for off-gassing before occupancy.


D.

Treat carpeting during install.


Questions # 32:

What is the PRIMARY purpose of the Incident Command System (ICS)?

Options:

A.

Coordinate effective response to any incident.


B.

Coordinate response to large incidents.


C.

Avoid duplication and provide better coordination efforts in any incident.


Questions # 33:

What does the effectiveness of infrastructure resilience rely on?

Options:

A.

Finance, security, supply chain, communications.


B.

Robustness, resourcefulness, rapid recovery, redundancy.


C.

Back-up power, capital planning, supply chain, security.


D.

Written incident response plans, training, management participation, employee adaptability.


Questions # 34:

What best describes Performance Measures?

Options:

A.

Performance indicators including metrics and drivers that achieve a given outcome.


B.

Pre-determined set of performance indicators and the actual results.


C.

Parameters and metrics that evaluate objectives against actual performance and goals.


Questions # 35:

Which network connection should the facility manager use for a 500-foot (150-meter) distance between a server and a department?

Options:

A.

Fiber optic


B.

Wireless


C.

Server purchase


D.

CAT 6 cable


Questions # 36:

What is an effective way to engage your staff in generating ideas that support the organization’s goal?

Options:

A.

Consider only those ideas of select staff.


B.

Roll out to the organization those processes which you believe are effective.


C.

Obtain feedback from staff and implement those ideas with positive feedback.


D.

Develop an open-door policy and dialogue with staff on how the team may help the organization achieve its goals.


Questions # 37:

What is typically NOT included in the evaluation process for investments in new equipment?

Options:

A.

NPV analysis


B.

Net Benefit analysis


C.

Root cause analysis


Questions # 38:

What approach should be taken to accommodate sustainability and customer concerns about installing flow restrictors?

Options:

A.

Take no action. The WPM is guided by company sustainability initiatives and this program needs to be implemented.


B.

Offer to place out the flow restrictors in a few designated restrooms to provide customer feedback on their performance. Agree to review and meet later with the WPM.


C.

Install the flow restrictors and remove them without informing the WPM.


D.

Refuse to install the flow restrictors.


Questions # 39:

What action should you take to address the premature aging of a roofing membrane?

Options:

A.

Plan and budget for replacing the roof system as soon as possible to prevent degradation or damage to other building components and contents.


B.

File a warranty claim with the manufacturer based on the membrane’s failure to reach its expected service life.


C.

Extend the service life of the roofing membrane with patches and repairs as leaks are detected until the full expected service life of the membrane is realized.


D.

Explain to occupants that water infiltration is expected in any facility and it will be addressed as an ongoing maintenance and repair item.


Questions # 40:

What purpose does project evaluation serve?

Options:

A.

To assess whether the project's objectives are being met


B.

To resolve claims and disputes in a timely manner


C.

To provide control of a project


D.

To track and monitor project progress